Hyperion Treatment Plant (HTP)
Secondary Clarifiers Upgrade (CIP 2422)

Project # W.O. SZH11722

 
Project Description
The Hyperion Treatment Plant Clarifiers Upgrade will rehabilitate the structural components that are experiencing severe corosion, at sixteen (four modules: modules 6-9) out of the thirty-six Secondary Clarifiers at HTP. These components included, but are not limited to: the entire catwalk system, flocculation support anchor rods and steel plate, the weir supports and associated anchor bolts, as well as the submerged steel componets (the rake-arm, flocculation well, ducking skimmer). This project will also replace the main drive motor and the rotating weir and its associated system.
 
Start Date   Estimated Completion Date
04/14/2014   04/14/2016

Amount
$7,976,000.00
 